Substation record 757S

Battle River

5 DTS MW is reported across 1 project in the surrounding Alliance/Battle River planning area, ranked 35 of 43 by listed DTS MW.

144/240 kVAlliance/Battle RiverCounty of Paintearth No. 18
Record

Substation details

The known physical and administrative context for this facility.

Facility code757S
Voltage144/240 kV
Planning areaAlliance/Battle River
Planning regionCentral
CountyCounty of Paintearth No. 18
DLS land description40-15-W4
Show on infrastructure map →
Connection Project List context

Projects in Alliance/Battle River

Stage 4 · AUC Applications1 project

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service.

Sort by
P2789 Red Willow Solar Battery
Project P2789
DTS 5 MWSTS 225 MWMW type: Solar + StorageProject type: ConnectionStage 4 · AUC ApplicationsActiveEN1 ISD 2028-08-31EN2 ISD 2028-08-31
Nearby infrastructure