Planning area

Alliance/Battle River planning area

A top-to-bottom view of transmission infrastructure and grid connection projects listed across the Alliance/Battle River planning area.

DTS MW in current Project List5 MW
Projects currently listed1
Tracked substations8

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service. Planning-area totals should not be attributed to a specific substation.

Substations

Infrastructure in Alliance/Battle River

Open a substation for its physical record, county context, and nearby facilities.

Connection projects

Projects listed in Alliance/Battle River

Connection process stage breakdown, and each project's published type, MW type, status, stage and reported in-service dates. A later stage number indicates further progress toward energization; Stage 6 is Close Out and can follow energization.

Stage 4 · AUC Applications1 project
P2789 Red Willow Solar Battery
Project P2789
DTS 5 MWSTS 225 MWMW type: Solar + StorageStage 4 · AUC ApplicationsActiveProject type: ConnectionEN1 ISD 2028-08-31EN2 ISD 2028-08-31