Planning area

Glenwood planning area

A top-to-bottom view of transmission infrastructure and grid connection projects listed across the Glenwood planning area.

DTS MW in current Project List75 MW
Projects currently listed3
Tracked substations11

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service. Planning-area totals should not be attributed to a specific substation.

Substations

Infrastructure in Glenwood

Open a substation for its physical record, county context, and nearby facilities.

Connection projects

Projects listed in Glenwood

Connection process stage breakdown, and each project's published type, MW type, status, stage and reported in-service dates. A later stage number indicates further progress toward energization; Stage 6 is Close Out and can follow energization.

Stage 2 · Assessment phase1 project
Stage 3 · Regulatory Preparation2 projects
P2880 Warner 344S DER Gas
Project P2880
STS 3.52 MWMW type: GasStage 3 · Regulatory PreparationRecently CancelledProject type: BTF
P3013 Raymond Reservoir Battery
Project P3013
STS 8.1 MWMW type: Battery StorageStage 3 · Regulatory PreparationActiveProject type: BTFEN1 ISD 2028-02-25
P3079 Captus Load
Project P3079
DTS 74.9 MWMW type: Data LoadStage 2 · Assessment phaseActiveProject type: ConnectionEN1 ISD 2027-09-01