Substation record MHS-2

North Industrial

56 DTS MW is reported across 8 projects in the surrounding Medicine Hat planning area, ranked 23 of 43 by listed DTS MW.

69/138 kVMedicine HatCypress County
Record

Substation details

The known physical and administrative context for this facility.

Facility codeMHS-2
Voltage69/138 kV
Planning areaMedicine Hat
Planning regionSouth
CountyCypress County
DLS land description13-6-W4
Show on infrastructure map →
Connection Project List context

Projects in Medicine Hat

Stage 1 · Assessment phase1 project
Stage 3 · Regulatory Preparation2 projects
Stage 5 · Construction5 projects

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service.

Sort by
P2517 Hutchison MPC Battery
Project P2517
DTS 50 MWSTS 100 MWMW type: Battery StorageProject type: ConnectionStage 3 · Regulatory PreparationActiveEN1 ISD 2029-11-22
P2467 Pteragen Peace Butte Wind
Project P2467
DTS 2 MWSTS 120 MWMW type: WindProject type: ConnectionStage 5 · ConstructionActiveEN1 ISD 2028-05-01
P3001 Midnight MPC Battery
Project P3001
DTS 2 MWSTS 200 MWMW type: Battery StorageProject type: ConnectionStage 3 · Regulatory PreparationActiveEN1 ISD 2029-10-18EN2 ISD 2029-10-18EN3 ISD 2029-10-18
P2461 Aira Solar
Project P2461
DTS 1 MWSTS 450 MWMW type: SolarProject type: ConnectionStage 5 · ConstructionActiveEN1 ISD 2027-12-15EN2 ISD 2027-12-15
P1828 hep Energy Alderson MPC Solar
Project P1828
DTS 0.5 MWSTS 100 MWMW type: SolarProject type: ConnectionStage 5 · ConstructionActiveEN1 ISD 2027-06-03EN2 ISD 2027-06-03EN3 ISD 2026-03-05
P2337 Dunmore Solar
Project P2337
DTS 0.5 MWSTS 216 MWMW type: SolarProject type: ConnectionStage 5 · ConstructionActiveEN1 ISD 2028-03-31EN2 ISD 2028-05-31
Nearby infrastructure

Nearby substations