Substation record 930S
Arcenciel
0 DTS MW is reported across 1 project in the surrounding Rainbow Lake planning area, ranked 40 of 43 by listed DTS MW.
Record
Substation details
The known physical and administrative context for this facility.
Facility code930S
Voltage144 kV
Planning areaRainbow Lake →Planning regionNorthwest
CountyNot available
DLS land description108-8-W6
Connection Project List context
Projects in Rainbow Lake
Stage 5 · Construction1 project
DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service.
No DTS projects to show.