Substation record 354S

Summerview

8 DTS MW is reported across 5 projects in the surrounding Fort Macleod planning area, ranked 30 of 43 by listed DTS MW.

138 kVFort MacleodM.D. of Pincher Creek No. 9
Record

Substation details

The known physical and administrative context for this facility.

Facility code354S
Voltage138 kV
Planning areaFort Macleod
Planning regionSouth
CountyM.D. of Pincher Creek No. 9
DLS land description7-28-W4
Show on infrastructure map →
Connection Project List context

Projects in Fort Macleod

Stage 3 · Regulatory Preparation4 projects
Stage 5 · Construction1 project

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service.

Sort by
P2619 Sweetgrass MPC Solar Battery
Project P2619
DTS 2 MWSTS 315 MWMW type: Solar + StorageProject type: ConnectionStage 3 · Regulatory PreparationActiveEN1 ISD 2028-06-01
P2806 Piikani Wind
Project P2806
DTS 2 MWSTS 153 MWMW type: WindProject type: ConnectionStage 3 · Regulatory PreparationActiveEN1 ISD 2028-02-28
P2445 Homestead MPC Solar
Project P2445
DTS 1.5 MWSTS 400 MWMW type: SolarProject type: ConnectionStage 5 · ConstructionActiveEN1 ISD 2027-03-01
P2503 Willow Ridge Battery
Project P2503
DTS 1.5 MWSTS 50 MWMW type: Battery StorageProject type: ConnectionStage 3 · Regulatory PreparationActiveEN1 ISD 2029-10-01EN2 ISD 2030-01-01
P2616 Jumbo Battery
Project P2616
DTS 1 MWSTS 218 MWMW type: Battery StorageProject type: ConnectionStage 3 · Regulatory PreparationActiveEN1 ISD 2028-04-01
Nearby infrastructure

Nearby substations