Substation record 275S

Jenner

6 DTS MW is reported across 3 projects in the surrounding Empress planning area, ranked 33 of 43 by listed DTS MW.

138/240 kVEmpress
Record

Substation details

The known physical and administrative context for this facility.

Facility code275S
Voltage138/240 kV
Planning areaEmpress
Planning regionSouth
CountyNot available
DLS land description20-8-W4
Show on infrastructure map →
Connection Project List context

Projects in Empress

Stage 4 · AUC Applications1 project
Stage 5 · Construction2 projects

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service.

Sort by
P2411 Northland Power Jurassic MPC Solar Battery
Project P2411
DTS 3.5 MWSTS 300 MWMW type: Solar + StorageProject type: ConnectionStage 5 · ConstructionActiveEN1 ISD 2026-03-09EN2 ISD 2026-04-01EN3 ISD 2028-01-15
P2418 Greencells Estuary Solar
Project P2418
DTS 1.5 MWSTS 200 MWMW type: SolarProject type: ConnectionStage 5 · ConstructionActiveEN1 ISD 2028-01-31EN2 ISD 2028-01-31
P2091 Arenosum Solar
Project P2091
DTS 1 MWSTS 150 MWMW type: SolarProject type: ConnectionStage 4 · AUC ApplicationsActiveEN1 ISD 2028-05-26