Substation record 142S

Magcan

451 DTS MW is reported across 6 projects in the surrounding High River planning area, ranked 11 of 43 by listed DTS MW.

138 kVHigh RiverFoothills County
Record

Substation details

The known physical and administrative context for this facility.

Facility code142S
Voltage138 kV
Planning areaHigh River
Planning regionSouth
CountyFoothills County
DLS land description19-28-W4
Show on infrastructure map →
Connection Project List context

Projects in High River

Stage 2 · Assessment phase1 project
Stage 3 · Regulatory Preparation1 project
Stage 4 · AUC Applications2 projects
Stage 5 · Construction2 projects

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service.

Sort by
P2926 Beacon Foothills A.I. Hub Load
Project P2926
DTS 400 MWMW type: Data LoadProject type: ConnectionStage 2 · Assessment phaseISD Under Review
P2520 Laramide MPC Battery
Project P2520
DTS 50 MWSTS 100 MWMW type: Battery StorageProject type: ConnectionStage 4 · AUC ApplicationsActiveEN1 ISD 2027-01-01
P2592 Big Rock Solar Battery
Project P2592
DTS 1 MWSTS 90 MWMW type: Solar + StorageProject type: ConnectionStage 4 · AUC ApplicationsRecently Cancelled
P2334 TCE Saddlebrook Solar Storage
Project P2334
DTS 0.2 MWSTS 87.5 MWMW type: Solar + StorageProject type: ConnectionStage 5 · ConstructionActiveEN1 ISD 2023-10-25EN2 ISD 2027-11-01
Nearby infrastructure

Nearby substations

Magcan (142S) Substation & Grid Context | GridLens