Planning area

Wabamun planning area

A top-to-bottom view of transmission infrastructure and grid connection projects listed across the Wabamun planning area.

DTS MW in current Project List3,209 MW
Projects currently listed15
Tracked substations21

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service. Planning-area totals should not be attributed to a specific substation.

Substations

Infrastructure in Wabamun

Open a substation for its physical record, county context, and nearby facilities.

Connection projects

Projects listed in Wabamun

Connection process stage breakdown, and each project's published type, MW type, status, stage and reported in-service dates. A later stage number indicates further progress toward energization; Stage 6 is Close Out and can follow energization.

Stage 1 · Assessment phase2 projects
Stage 2 · Assessment phase8 projects
Stage 3 · Regulatory Preparation4 projects
Stage 5 · Construction1 project
P2462 Fortis Stony Plain 434S DER Solar
Project P2462
STS 12.2 MWMW type: SolarStage 5 · ConstructionActiveProject type: BTFEN1 ISD 2026-09-04
P2826 Paul Band Solar
Project P2826
DTS 0.5 MWSTS 37 MWMW type: SolarStage 3 · Regulatory PreparationActiveProject type: ConnectionEN1 ISD 2028-07-30
P2881 South Mayerthorpe 443S DER Gas
Project P2881
STS 3.8 MWMW type: GasStage 3 · Regulatory PreparationRecently CancelledProject type: BTF
P2927 Beacon Harry Smith A.I. Hub Load
Project P2927
DTS 400 MWMW type: Data LoadStage 2 · Assessment phaseISD Under ReviewProject type: Connection
P2942 Genesee Data Center 1 MPC Load
Project P2942
DTS 1,000 MWMW type: Data LoadStage 2 · Assessment phaseISD Under ReviewProject type: Connection
P2946 Genesee Data Center 2 MPC Load
Project P2946
DTS 500 MWMW type: Data LoadStage 2 · Assessment phaseISD Under ReviewProject type: Connection