Planning area

Strathmore/Blackie planning area

A top-to-bottom view of transmission infrastructure and grid connection projects listed across the Strathmore/Blackie planning area.

DTS MW in current Project List952 MW
Projects currently listed5
Tracked substations8

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service. Planning-area totals should not be attributed to a specific substation.

Substations

Infrastructure in Strathmore/Blackie

Open a substation for its physical record, county context, and nearby facilities.

Connection projects

Projects listed in Strathmore/Blackie

Connection process stage breakdown, and each project's published type, MW type, status, stage and reported in-service dates. A later stage number indicates further progress toward energization; Stage 6 is Close Out and can follow energization.

Stage 2 · Assessment phase1 project
Stage 3 · Regulatory Preparation1 project
Stage 5 · Construction3 projects
P2378 RESC Nova MPC Solar
Project P2378
DTS 1 MWSTS 150 MWMW type: SolarStage 5 · ConstructionActiveProject type: ConnectionEN1 ISD 2027-08-01
P2396 Georgetown Solar
Project P2396
DTS 1 MWSTS 230 MWMW type: SolarStage 5 · ConstructionActiveProject type: ConnectionEN1 ISD 2028-12-01
P2451 Georgetown Battery Addition
Project P2451
MW type: Battery StorageStage 5 · ConstructionActiveProject type: BTFEN1 ISD 2028-12-15
P2751 Hussar 431S Battery
Project P2751
STS 20 MWMW type: Battery StorageStage 3 · Regulatory PreparationActiveProject type: BTFEN1 ISD 2027-04-01
P3102 Goldfinch Technology Park MPC Load
Project P3102
DTS 950 MWMW type: Data LoadStage 2 · Assessment phaseISD Under ReviewProject type: Connection