Planning area

Red Deer planning area

A top-to-bottom view of transmission infrastructure and grid connection projects listed across the Red Deer planning area.

DTS MW in current Project List498 MW
Projects currently listed7
Tracked substations19

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service. Planning-area totals should not be attributed to a specific substation.

Substations

Infrastructure in Red Deer

Open a substation for its physical record, county context, and nearby facilities.

Connection projects

Projects listed in Red Deer

Connection process stage breakdown, and each project's published type, MW type, status, stage and reported in-service dates. A later stage number indicates further progress toward energization; Stage 6 is Close Out and can follow energization.

Stage 2 · Assessment phase3 projects
Stage 3 · Regulatory Preparation2 projects
Stage 4 · AUC Applications1 project
Stage 6 · Close Out1 project
P2602 Collisard MPC Gas
Project P2602
DTS 3 MWSTS 120 MWMW type: GasStage 4 · AUC ApplicationsActiveProject type: ConnectionEN1 ISD 2029-01-31EN2 ISD 2029-01-31
P2981 Myers Energy Park MPC Gas
Project P2981
DTS 3 MWSTS 178 MWMW type: GasStage 2 · Assessment phaseRecently CancelledProject type: Connection
P2982 Gilby Power Park MPC Gas
Project P2982
DTS 3 MWSTS 178 MWMW type: GasStage 2 · Assessment phaseRecently CancelledProject type: Connection
P3034 Valley Edge Battery
Project P3034
DTS 200 MWSTS 250 MWMW type: Battery StorageStage 3 · Regulatory PreparationActiveProject type: ConnectionEN1 ISD 2028-10-01
P3040 AHI Prairie Eagle Cogen
Project P3040
DTS 10 MWSTS 150 MWMW type: Cogen + Solar + StorageStage 3 · Regulatory PreparationISD Under ReviewProject type: Connection
P3155 Myers Energy Park MPC Data Load
Project P3155
DTS 280 MWMW type: Data LoadStage 2 · Assessment phaseRecently CancelledProject type: Connection