Grande Prairie planning area

A top-to-bottom view of transmission infrastructure and grid connection projects listed across the Grande Prairie planning area.

DTS MW in current Project List93 MW
Projects currently listed8
Tracked substations21

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service. Planning-area totals should not be attributed to a specific substation.

Substations

Infrastructure in Grande Prairie

Open a substation for its physical record, county context, and nearby facilities.

Connection projects

Projects listed in Grande Prairie

Connection process stage breakdown, and each project's published type, MW type, status, stage and reported in-service dates. A later stage number indicates further progress toward energization; Stage 6 is Close Out and can follow energization.

Stage 2 · Assessment phase1 project
Stage 3 · Regulatory Preparation6 projects
Stage 4 · AUC Applications1 project
P2256 ATCO Poplar Hill Load
Project P2256
DTS 34.5 MWMW type: Distribution LoadStage 4 · AUC ApplicationsActiveProject type: ConnectionEN1 ISD 2027-05-25
P2716 Wapiti 823S Load
Project P2716
DTS 28 MWMW type: Distribution LoadStage 3 · Regulatory PreparationActiveProject type: ConnectionEN1 ISD 2028-04-01
P2843 Prairie Lights Power Gas
Project P2843
DTS 5 MWSTS 310 MWMW type: GasStage 3 · Regulatory PreparationActiveProject type: ConnectionEN1 ISD 2028-06-01EN2 ISD 2028-06-01
P2944 Mowat 2033S DER Gas
Project P2944
STS 19 MWMW type: GasStage 3 · Regulatory PreparationActiveProject type: BTFEN1 ISD 2027-04-01
P3006 Clairmont Energy Gas
Project P3006
DTS 20 MWSTS 178 MWMW type: GasStage 3 · Regulatory PreparationActiveProject type: ConnectionEN1 ISD 2029-05-01EN2 ISD 2029-06-01
P3069 Prairie Lights Power Unit 2 MPC Gas
Project P3069
STS 466 MWMW type: GasStage 3 · Regulatory PreparationActiveProject type: ConnectionEN1 ISD 2028-02-15EN2 ISD 2029-06-01