A top-to-bottom view of transmission infrastructure and grid connection projects listed across the Edmonton planning area.

DTS MW in current Project List777 MW
Projects currently listed13
Tracked substations45

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service. Planning-area totals should not be attributed to a specific substation.

Substations

Infrastructure in Edmonton

Open a substation for its physical record, county context, and nearby facilities.

Connection projects

Projects listed in Edmonton

Connection process stage breakdown, and each project's published type, MW type, status, stage and reported in-service dates. A later stage number indicates further progress toward energization; Stage 6 is Close Out and can follow energization.

Stage 1 · Assessment phase2 projects
Stage 2 · Assessment phase4 projects
Stage 3 · Regulatory Preparation3 projects
Stage 4 · AUC Applications1 project
Stage 5 · Construction3 projects
P2453 EDTI Edmonton 3 H2 Plant Cogen
Project P2453
DTS 50 MWSTS 20 MWMW type: CogenStage 5 · ConstructionActiveProject type: ConnectionEN1 ISD 2026-12-01EN2 ISD 2027-05-01
P2582 Woodcroft Reliability
Project P2582
MW type: Equipment ChangeStage 5 · ConstructionActiveProject type: ConnectionEN1 ISD 2026-10-30EN2 ISD 2027-07-31EN3 ISD 2028-04-30
P2656 Edmonton CCUS Gas
Project P2656
DTS 3 MWSTS 94 MWMW type: GasStage 4 · AUC ApplicationsActiveProject type: ConnectionEN1 ISD 2029-03-31EN2 ISD 2029-06-30
P2935 Beacon Saunders Lake A.I. Hub Load
Project P2935
DTS 400 MWMW type: Data LoadStage 2 · Assessment phaseISD Under ReviewProject type: Connection
P2972 SW Edmonton Area Load Meadowlark Upgrade
Project P2972
MW type: Distribution LoadStage 5 · ConstructionActiveProject type: ConnectionEN1 ISD 2026-12-02EN2 ISD 2028-12-02EN3 ISD 2030-12-02
P3014 Meadowview Solar Battery
Project P3014
DTS 66 MWSTS 135 MWMW type: Solar + StorageStage 3 · Regulatory PreparationActiveProject type: ConnectionEN1 ISD 2029-10-01EN2 ISD 2029-10-01