Planning area

Caroline planning area

A top-to-bottom view of transmission infrastructure and grid connection projects listed across the Caroline planning area.

DTS MW in current Project List1,864 MW
Projects currently listed2
Tracked substations9

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service. Planning-area totals should not be attributed to a specific substation.

Substations

Infrastructure in Caroline

Open a substation for its physical record, county context, and nearby facilities.

Connection projects

Projects listed in Caroline

Connection process stage breakdown, and each project's published type, MW type, status, stage and reported in-service dates. A later stage number indicates further progress toward energization; Stage 6 is Close Out and can follow energization.

Stage 2 · Assessment phase1 project
Stage 5 · Construction1 project
P2627 Sundre 575S DER Solar
Project P2627
STS 12.6 MWMW type: SolarStage 5 · ConstructionISD Under ReviewProject type: BTF
P3066 Leedale Data Load
Project P3066
DTS 1,864 MWMW type: Data LoadStage 2 · Assessment phaseISD Under ReviewProject type: Connection