Planning area

Athabasca/Lac La Biche planning area

A top-to-bottom view of transmission infrastructure and grid connection projects listed across the Athabasca/Lac La Biche planning area.

DTS MW in current Project List0 MW
Projects currently listed1
Tracked substations18

DTS and STS figures represent contract-capacity changes reported in the Connection Project List. They do not represent available transmission capacity, current site demand, or guaranteed service. Planning-area totals should not be attributed to a specific substation.

Substations

Infrastructure in Athabasca/Lac La Biche

Open a substation for its physical record, county context, and nearby facilities.

Connection projects

Projects listed in Athabasca/Lac La Biche

Connection process stage breakdown, and each project's published type, MW type, status, stage and reported in-service dates. A later stage number indicates further progress toward energization; Stage 6 is Close Out and can follow energization.

Stage 2 · Assessment phase1 project
P3144 Westlock-WST1 Modification
Project P3144
MW type: Equipment ChangeStage 2 · Assessment phaseActiveProject type: BTFEN1 ISD 2027-09-30